Automated recovery for construction materials

Rino Recycling’s A$95 million facility at Pinkenba, Brisbane, combines automated processing with the recovery of materials for new infrastructure projects. General Manager Dan Blaser said the plant can handle up to 475 tonnes of waste per hour, with potential annual processing of more than 1.5 million tonnes and a recovery rate of 97%.

Rino’s Pinkenba site stands 13 kilometres from Brisbane’s central business district. Director Todd Pepper said the site could reduce journeys to landfill facilities west of the city, including Swanbank in Ipswich. Blaser linked demand for recovered materials to Brisbane’s infrastructure pipeline, the SEQ City Deal and preparations for the 2032 Olympics.

Rino construction and operational milestones
Construction began before testing and operation.

Wet and dry systems under one roof

Construction began in January 2023. Performance testing was complete and the plant operational by February 6, 2024. Rino brought together Turmec’s dry separation equipment and CDE’s wet processing technology. Four feeder points accommodate different incoming materials:

  • Construction waste;
  • Skip bin waste;
  • Dirty fill and excavation waste;
  • Liquid waste, including non-destructive digging material and street sweepings.

CDE designed, built and commissioned the wet section. Its equipment covers HydroVac and wet waste retrieval, aggregate scrubbing, beneficiation and sand washing. CDE General Manager for Australasia Daniel Webber said the water recovery system recycles more than 90% of the plant’s water needs.

Wet aggregate recovery and grading equipment
Construction aggregate recovery; thematic processing scene.

Turmec and CDE integrated wet and dry waste handling into a single automated production line. Turmec’s contribution centres on dry separation, while CDE supplies the washing processes. The resulting material streams include aggregates and road base for construction applications.

Turmec also identified potential use of the remaining residual material as fuel for industrial boilers. This forms a separate prospective outlet alongside the recovered construction products. The supplier’s work with Rino focused on integrating the varied feedstocks into an automated separation system.

Turmec recycling technology wordmark
Turmec supplied dry separation technology.

Water reuse and material quality

A wet density separator on the aggregate line removes lightweight impurities, including tiles, masonry and heavy plastics. Heavier aggregates can serve concrete production. Outputs include aggregates, road base and washed sand for construction.

Rino’s facility also has an acre of rooftop solar panels. Its water system recirculates 35,000 litres per hour, according to the company. Blaser said a truck could unload construction waste and depart with recycled products in under 20 minutes.

Company and contact details

Rino Recycling
45 Eagle Farm Road, Pinkenba QLD 4008
Phone: 07 3260 2100
Media: marketing@rinorecycling.com.au
Sales: sales@rinorecycling.com.au
Website: Rino Recycling