First production line commissioned at Port Kembla

Hysata has commissioned the first production line for HysataFab, its manufacturing platform for electrolyser components, at its 8,500-square-metre headquarters in Port Kembla, New South Wales. The Australian manufacturer is combining real-time monitoring, robotics and inline quality testing in the facility. The electrode line is operational, while the membrane and cell-and-stack lines are to follow. Hysata describes the platform as a repeatable manufacturing template that could be deployed at additional locations as demand develops.

The initial manufacturing programme is designed for 50 MW of electrolyser capacity annually on a single shift. Continuous operation could raise that figure to 200 MW per year. These are manufacturing-capacity figures, rather than hydrogen output or electricity generation. The three production lines cover:

  • Electrode manufacturing.
  • Membrane manufacturing.
  • Cell and stack manufacturing.
Electrode launch precedes planned export delivery
Commissioned line and planned customer delivery.

Public funding and production data

The Port Kembla project represents an investment of close to A$100 million. A grant of A$49 million through the Australian Renewable Energy Agency’s Future Made in Australia Innovation Fund will support manufacturing establishment and scale-up, with Hysata matching the contribution from private capital. The company distinguishes that manufacturing support from the development of its AI platform, which it funded itself. The first electrode line was commissioned on 18.09.2026, when Hysata announced the launch of the platform.

Hysata says it has accumulated more than 57 billion process data points over three years and generates more than 100 million additional points daily. Its electrode line analyses component data during production and feeds information back into process control. The company expects AI optimisation to increase output by up to 15% compared with the same physical line without that optimisation.

Australian Renewable Energy Agency wordmark
ARENA supports manufacturing establishment and scale-up.

Qualification and customer deliveries

The ARENA-supported scale-up project runs from 15.07.2026 to a planned completion on 31.01.2029. Its programme includes installing, commissioning and qualifying production equipment, processes and quality controls, alongside manufacturing improvements and supply-chain qualification. Hysata is also to manufacture, test and deliver two early megawatt-scale customer systems. The intended project outcome is a qualified line capable of 50 MW per year on a single shift, with additional throughput available through further shifts as demand grows. Manufacturing and operating data from the early systems will support subsequent development.

Hysata signed its first binding megawatt-scale export order in June 2026 with a global heavy-industry customer. Delivery is scheduled for the first half of 2027, and electrodes for that system are to be manufactured through HysataFab.

Inline inspection in component manufacturing
Component inspection and process control; thematic scene.